This bridge now has suicide prevention fencing.
|
|
|
Hello!We
thank you for your patience and understanding as we finalize remaining
work on Pacific Street from Hornby to Howe Street as part of the
Burrard Street Corridor Project. Construction: What to Expect in FebruarySome
of the finishing touches along Pacific Street to improve street
lighting and conditions for people walking and cycling have been delayed
due to additional third party utility works. We apologize for this
inconvenience and will complete this section in early 2018, once the
electrical system upgrades are wrapped up.
Access to residences and businesses will be maintained at all times during construction. Lighting of the Memorial Braziers
On Tuesday, January 23, the brazier lights at each end of Burrard Bridge were lit once again in honour of our Canadian veterans.
The
City extends a warm thank you to the Royal United Services Institute of
Vancouver and the Vancouver Heritage Foundation for their extensive
work in facilitating the restoration of the brazier lights.
|
|
|
|
|
|
Red Bridge Lights to Mark Winter OlympicsThe
restored pedestrian lights on the bridge will glow red during the
upcoming 2018 Winter Olympics as part of the City's efforts to support
and celebrate our Canadian athletes. ABOUT THE BURRARD CORRIDOR PROJECTThe
City has replaced aging water, sewer, and street infrastructure,
improved safety for all modes of transportation at the Burrard-Pacific
intersection, and has provided needed structural rehabilitation
for Burrard Bridge.
Project information & newsletter
sign-up:
vancouver.ca/burrardcorridor TransLink
updates:
translink.ca/alerts Email:
burrardstreet@vancouver.ca
|
|
|
|
|
|
|